The City of Chattanooga is moving forward with constructing a modern Fire Station 14 facility to bolster emergency response capabilities and safety infrastructure across the South Chattanooga and St. Elmo communities. The new station will replace the existing, structurally impaired facility on W 39th Street—which was originally built in 1974—and relocate operations to a new site in the 3800 block of Ohls Avenue.

Fire Station 14 Rebuild
Project Highlights
- Relocation & Upgrade: Relocates the older 1009 W 39th Street single-company station to a new site on Ohls Avenue, resolving long-standing structural issues.
- Enhanced Response Capabilities: Upgrades facility capacity to better serve the surrounding residential, commercial, and historical St. Elmo areas.
- Safety & Modernization: Provides modern apparatus bays, equipment housing, and health/wellness amenities for first responders.
Project Timeline
Start Date: Late 2026 (Subject to MOU finalization)
The Rebuild of Fire Station 14 is currently in the Planning phase.
- Design & Site Prep: Site address finalization and phase 1 environmental/soil testing are currently active.
- Agreements: Finalizing the Memorandum of Understanding (MOU) to finalize site transfer and construction milestones.
- Groundbreaking: Physical construction is projected to commence in late 2026 once design and site testing wrap up.
Project Budget
The budget allocation and managing framework for the new facility:
- Funding Source: City of Chattanooga Capital Improvement Plan (FY 2026/2027 Capital Budget Allocation)
- Managing Department: City of Chattanooga Fire Department & Public Works