Heritage Landing Drive Culvert Repair
The City is taking the following steps to repair what initially appeared to be a sinkhole on Heritage Landing Drive. It was later determined to be a collapsed storm drain beneath the road:
Project Highlights
- Installing New Piping: We are using a "trench-less" boring method to install a high-capacity 42-inch pipe toward the river without disturbing the entire surface.
- System Upgrade: We are connecting the neighborhood's current drainage into this new, stronger system and closing off the old, damaged pipe.
- Road Restoration: Once the new pipes and manholes are in place, we will fill the collapsed area with stable material and repair the damage to the road.
Project Timeline
Expected Completion: April 15, 2026
The Heritage Landing Drive Culvert Repair Project is currently in the In Progress phase. The project is expected to be completed by April 15, 2026.
Project Budget
Budget: $1,169,900
Contingency: $121,000
The budget reflect the complexity and future-proofing our infrastructure based on the three distinct aspects of the project: upgrading the drainage system, stabilizing and filling in the collapsed area, and repairing the road. The expected project budget is $1,169,900 with a contingency of $121,000 in case other issues or complications arise as work progresses.
Heritage Landing Images
Great news for the community: Heritage Landing Drive will officially reopen on March 25th! Our road crews are currently on-site retrieving barriers and removing detour signage to restore normal traffic flow. While the road is fully accessible, please note that final striping will take place in the near future; this work will be scheduled outside of peak hours to ensure it does not disrupt your commute.
View More Updates